Crane on Tyra II Process Module Now in Permanent Use

OE Staff
Tuesday, December 27, 2022

Norwegian Energy Company (Noreco) said Friday it had reached a milestone on the hook-up and commissioning campaign of Tyra II with the crane on the process module (the "TEG") now in permanent use. 

"The milestone was planned for early Q1 2023 and is as such achieved ahead of schedule despite the challenging weather conditions earlier this month," Noreco said.

According to Noreco, the TEG crane is important for the project as it enables an efficient completion of the remaining scope of the hook-up, commissioning, and start-up of Tyra II.

Due to seabed subsidence, the Tyra field required a redevelopment, calling for the removal and decommissioning of the prior Tyra platforms, reuse, and a 13-meter extension of the existing jackets at six platforms, and the construction and installation of new topsides, a new processing platform, and a new accommodation platform.

In October, TotalEnergies, the project operator, said that it had completed the offshore installation works at the Tyra II field redevelopment project in the Danish North Sea. This was related to the installation of new facilities.

Earlier this month,  TotalEnergies said that the old platforms had been recycled.

First gas from Tyra II is slated for the winter season 2023/24


Categories: Energy Engineering North Sea Industry News Activity Europe Construction Cranes

Related Stories

TWMA Hooks ‘Major Contract’ with BP in North Sea

Viaro Energy Appoints Exceed as Well Operator for Over 190 North Sea Wells

Use of Drones for Improved Security of Oil and Gas Up for North Sea Trials

Current News

National Grid Takes $402 Million Hit on Paused New York Wind Project

Libya's Latest Oil and Bidding Round Attracts Over 40 Applicants

Mitsui’s STATS Rolls Out Titanium Connector for Oil and Gas Sector

Indonesia Grants Approval to Kuwaiti Firm for Anambas Block in Natuna Sea

Subscribe for OE Digital E‑News