Jan De Nul Completes Installation of Trianel Windpark Borkum II Wind Turbines

Tuesday, June 23, 2020

Jan De Nul Group last week completed the offshore Trianel Windpark Borkum II (TWBII) project in the German North Sea.

"All 32 Wind Turbine Generators (WTG) have been installed and mechanically completed," Jan de Nul said last Friday.

Jan De Nul Group’s Jack-Up ƶijϻ Installation Vessel (JUIV) Taillevent started the Wind Turbine Generator installation works in the summer of 2019 but had to leave mid-February 2020 to undertake commitments in Taiwan. 

The installation works of the remaining WTGs were completed with the Blue Tern vessel.

Jan De Nul Group and its Subcontractor Global Wind Service subsequently finalized the mechanical completion of the 32 WTGs in order to have them ready for commissioning by TWBII, Jan De Nul said.

Jan De Nul Group was awarded the WTG installation works by Senvion in December 2017, after which the start of the WTG installation works was delayed due to Senvion’s insolvency proceedings. 

The offshore wind farm Trianel Wind Park Borkum (Phase II) comprises 32 offshore WTG of 6.33 MW each. The scope of Jan De Nul Group included both the offshore installation of the WTGs and the mechanical completion works.


Watch the recording of World Energy Report's ƶijϻ Wind Webinar 

Categories: Energy Vessels Industry News Europe ƶijϻ Wind

Related Stories

DEME Acquires 50% Stake in BAUER ƶijϻ Technologies

Certek Acquires Wind Turbine Services Firm GEV Wind Power

North Star Takes Delivery of its First CSOV (Video)

Current News

Industry Leaders Set to Discuss Future of US ƶijϻ CCS Market

Polish Shipbuilder Lays Keel for DOF’s New ƶijϻ Support Vessel

ADNOC Partners with ExxonMobil, Occidental to Boost UAE Oil and Gas Capacity

Estonia Grants First ƶijϻ Wind Construction Permit

Subscribe for OE Digital E‑News