Formosa 1 Phase 2 Foundations Installed

Tuesday, August 20, 2019

Jan De Nul Group said it has installed all 20 foundations for the 120-megawatt (MW) Formosa 1 Phase 2 wind farm offshore Taiwan.

As part of the Dutch company mobilized the Seaway Yudin to install the foundations as part of its EPCI contract for building of the overall balance of plant.

The foundations consist of a monopile and transition piece structure with a grouted connection. The monopiles range from 752 to 1,230 tons, with a maximum diameter of 8.4 meters and a length ranging from 60.1 to 79.5 meters. Each of the transition pieces weigh 465 tons and consists of five internal platforms, an external platform and boat landing.

Over a period of less than one year, Jan De Nul completed the fabrication process, the sea transport, the load in and out at the marshaling harbor in the Port of Taichung, and finally the installation of all foundations offshore.

The parallel installation of scour protection, export and inter array cables is also well underway, Jan De Nul said.

The wind farm is owned by Formosa I Wind Power Co. Ltd., a partnership of Ørsted (35%), JERA (32.5%), Macquarie Capital (25%) and Swancor Holding (7.5%).

The offshore wind farm is located around 6 kilometers off the west coast of the Miaoli district in the Taiwan Strait, with water depths ranging between 15 and 30 meters. The project comprises 2 phases: phase 1 of two wind turbines with a total capacity of 8MW. Extended from phase 1, this second phase will add 20 offshore wind turbines with a total capacity of 120MW to Formosa 1's current 8MW capacity. Formosa 1 will be the first commercial-scale offshore wind farm in Taiwan before 2020.

Categories: ƶijϻ ƶijϻ Energy Engineering Activity Asia Renewables Installation

Related Stories

Seatools Gets Fengmiao 1 ƶijϻ Wind Job from CDWE

ESVAGT, KMC Line to Launch ƶijϻ Wind JV in South Korea

Van Oord Starts Construction Works at RWE’s German ƶijϻ Wind Farm

Current News

National Grid Takes $402 Million Hit on Paused New York Wind Project

Libya's Latest Oil and Bidding Round Attracts Over 40 Applicants

Mitsui’s STATS Rolls Out Titanium Connector for Oil and Gas Sector

Indonesia Grants Approval to Kuwaiti Firm for Anambas Block in Natuna Sea

Subscribe for OE Digital E‑News