Albatros Topside Installed

Wednesday, March 27, 2019

The topside of the offshore substation at the Albatros wind farm offshore Germany was installed Tuesday evening, developer EnBW said.

The heavy-lift jack-up vessel (HLJV) Pacific Ospray had loaded the topside in Rotterda, and once in the construction area, the HLJV Innovation lifted the topside on the foundation (monopile and transition piece) that had already been installed. 

The Pacific Ospray will be jacked up and remain next to substation until outstanding coating and welding work is completed.

Afterwards, the jack-up vessel Seafox2 will come to commission the offshore substation.

Categories: Engineering Activity Europe Renewables Installation

Related Stories

Shell and Google Enter PPA to Extend Life of First Dutch ƶijϻ Wind Farm

Sentinel Subsea Completes Well Monitoring Job in North Sea

ONGC Buys Viridien’s Sercel ƶijϻ Logistics Solution

Current News

Industry Leaders Set to Discuss Future of US ƶijϻ CCS Market

Polish Shipbuilder Lays Keel for DOF’s New ƶijϻ Support Vessel

ADNOC Partners with ExxonMobil, Occidental to Boost UAE Oil and Gas Capacity

Estonia Grants First ƶijϻ Wind Construction Permit

Subscribe for OE Digital E‑News