2015 Barryroe drilling planned

Friday, September 19, 2014

Planning is underway for further drilling on the Barryroe discovery in the Celtic Sea offshore Ireland during 2015 with a view to reaching first oil by 2018, according to partner Landsdowne Oil & Gas. 

The work is subject to a farm-out deal being reached on on Barryroe by operator Providence Resources, in order to raise the cash to develop the field. According to Landsowne, a deal is "nearing completion."

Lansdowne says Providence envisages a staged development on Barryrow, with Phase 1 using a floating production, storage and offloading vessel to produce up to 30,000b/d from the area around the 48/24-10z well.

Subsequently, a Phase 2 is anticipated to involve a number of fixed platforms, resulting in peak output of up to 100,000b/d.

Discovered in the 1970s by Marathon, Barryroe wasn’t pursued due to high state participation (50% pre-1992) and an unfavorable tax regime. The oil was also waxy, which at the time had technical and economic implications, both of which are no longer a problem, according to Providence. 

Read more:

Categories: Drilling FPSO Europe Oil Production Floating Production

Related Stories

SLB Launches New Well Completions Tech to Boost Production

Aker BP Secures Drilling Permit for Multiple Wildcat Wells in North Sea

TWMA Hooks ‘Major Contract’ with BP in North Sea

Current News

Industry Leaders Set to Discuss Future of US ƶijϻ CCS Market

Polish Shipbuilder Lays Keel for DOF’s New ƶijϻ Support Vessel

ADNOC Partners with ExxonMobil, Occidental to Boost UAE Oil and Gas Capacity

Estonia Grants First ƶijϻ Wind Construction Permit

Subscribe for OE Digital E‑News