Deutsche Bucht ƶijϻ Wind Substation Nears Completion

Posted by Michelle Howard
Wednesday, November 21, 2018

Ten months after the final assembly of the offshore substation (OSS) for the new Deutsche Bucht offshore wind farm started at Damen Shiprepair Vlissingen (DSV), the substation topside has now been moved outside the construction hall so that further outfitting can take place.

The Deutsche Bucht offshore wind farm, owned by Northland Power, will have 33 turbines, situated 95 kilometers northwest of Germany’s Borkum Island, in the North Sea. The wind farm will have a total capacity of 269 MW.

Van Oord is managing the overall Balance of Plant scope, including the OSS project, with the joint venture Iemants-Eiffage contracted for the engineering, procurement, construction and installation of the substation topside and jacket. Together with Damen Schelde Naval Shipbuilding, DSV is managing the yard facilities and supporting the OSS works by providing welding and painting services.

ƶijϻ installation is planned in the first half of 2019.

Categories: ƶijϻ Wind Power Renewable Energy Engineering Europe Construction Renewables

Related Stories

Topside for Hollandse Kust (west Beta) Substation Set to Sail to Final Location

DEME Acquires 50% Stake in BAUER ƶijϻ Technologies

Scarborough FPU's Topsides and Hull Come Together in Major Engineering Feat (Video)

Current News

Industry Leaders Set to Discuss Future of US ƶijϻ CCS Market

Polish Shipbuilder Lays Keel for DOF’s New ƶijϻ Support Vessel

ADNOC Partners with ExxonMobil, Occidental to Boost UAE Oil and Gas Capacity

Estonia Grants First ƶijϻ Wind Construction Permit

Subscribe for OE Digital E‑News